Expedition ship "MS Finnmarken"

Dedicated Sales Team

Our worldwide presence ensures the timeliness, cost efficiency compliance adherence required to ensure your vessel timelines are met.

SCOPE:

  • Cabins + corridor area
  • Public zones (Explorer lounge, Wellness, Sauna, Gym, Stair Halls)

DURATION:

  • 2 months

WORKERS:

  • ~150

WORKS DONE:

  • Dismounting, supply and installation of floor (carpet, tiles) 2200m2
  • Dismounting supply and installation of new panels 2200m2
  • Dismounting supply and installation of new ceiling 2200m2
  • Supply of furniture for working areas 2200m2
  • Installation of electrical part for working areas 2200m2